Water Storage Tank and Pump Station
IMEG and Gene Schaefer from SDG are currently working with Castle Pines Metro District to design and construct a new 2.0 MG buried water storage tank and pump station. The proposed tank will provide additional storage capacity for the District during peak usage periods while the pump station transfers water to the appropriate zones.
The proposed tank is a post tensioned concrete tank (approximately 1.9 MG) for potable water, and transfer pump station, including ancillary work items such as connecting potable water piping, site grading, etc. When the project was originally bid, the cost came in higher than expected due to the change in the construction market. IMEG and the District are now evaluating different tank sites as cost saving alternatives.