Loudoun County Aldie Fire Station #7
The project: The new Loudoun County Station, Aldie Fire Station 7, is a 23,000-sf facility that includes apparatus bays, bunk rooms, a training room, break room, restrooms, showers, food preparation area, dining area, laundry room, decontamination area, supply storage, a gear and hose drying area, breathing apparatus air compressor room, fitness room, offices, and a repair shop.
Challenges and Solutions: From the initial planning stages to the final construction documentation, the civil design team delivered a site solution that met the operational needs of the station while addressing the challenges of the site’s topography, environmental sensitivity, and infrastructure demands.
The site layout was strategically developed to optimize functionality and response times while maintaining compatibility with the surrounding rural context. The station’s orientation maximized accessibility for emergency vehicles and provided efficient internal circulation.
Grading was a critical component of the design. A balanced cut-and-fill strategy minimized earthwork, controlled construction costs, and preserved the natural character of the site. The grading design provided positive drainage, ensured ADA-compliant access, and supported the architectural requirements of the building footprint.
The utility infrastructure was designed to provide reliable service connections while accommodating future expansion. This included the extension and coordination of water, sanitary sewer, and
dry utilities with local service providers. The utility design also integrated with on-site features to avoid conflicts and supported efficient construction phasing.
The project incorporated a robust erosion and sediment control plan. Temporary and permanent measures—including silt fences, sediment basins, and stabilized construction entrances—were implemented to protect nearby water bodies and minimize soil loss during construction.
A comprehensive stormwater management system was developed to meet regulatory requirements and promote sustainable site development. The design featured a detention system to manage runoff quantity and improve water quality. These solutions were seamlessly integrated into the landscape and supported by detailed hydrologic and hydraulic analysis.
Throughout the design process, value engineering played a key role in optimizing project outcomes. The team evaluated alternative materials, construction methods, and site configurations to reduce costs without compromising performance or design intent. The final construction documents included a complete set of civil drawings and technical specifications tailored to the project’s needs. These documents provided clear guidance for contractors and ensured that all civil elements—from paving sections to storm structures—were constructed to a high standard of quality.
Project Outcome: IMEG successfully delivered a compliant and context-sensitive design. Through proactive planning, environmental stewardship, and collaboration with stakeholders, the civil design preserved natural and historic resources while supporting the operational mission of the fire station.